Installation and Commissioning of Rotary Impact Crusher
The scientific management of the impact crusher is a very important part for the management of the comprehensive quality of the crushing equipment. The scientific management of the impact crusher runs through the whole process of the reasonable design, production and manufacturing, packaging, transportation, installation and commissioning, safe operation, maintenance and repair. The above stages have an extremely close relationship. If the blocking phenomena often appear in the impact crusher with some type in the actual use, the structure design of the machine should be further improved. Therefore, we should consider the problem from the size of the section area of the feeding port and the height size or the cross-sectional size of the whole crushing cavity. In short, the structural design of the crushing chamber should meet the principle of smooth feeding and discharging. This article will detailed explore the installation and commissioning of the rotary impact crusher.
After unpacking, you should check if the spare parts, spare parts, manuals, certificates and other design documents are complete according to the container loading list. If the parts are not enough, you should contact with the manufacturer in a timely manner. You should carefully check the related size for the installation of the main parts. You should specially note that if the base drawings, foundation and the material objects are coincident. If they are not coincident, you should correct them and then install them. After the size check, you should thorough clean the parts. After cleaning, you should particularly careful to protect the friction surface of the parts in order to prevent dust pollution and to prevent the damage to the friction surface. If the parts are not installed in a timely manner, they need to be kept well. Coat the surface with oil to prevent rust.
There is a base plate under the rack of the crushing machine to adjust the balance. After long-time use of the machine, you should repair it or replace it. The position of the base plate should be close to the foundation bolt. Cleaning the foundation before the installation is very important. You should clean the aggradation and sundries on the foundation.
We provide Professional technology, excellent product quality and intimate after-sales service when you purchase Cement mill, Compound Cone Crusher, Ball Grinder, from our company.As a professional mining machinery exporter, we will win your trust with our delivery speed, Enterprises Credit and product quality.
订阅:
博文评论 (Atom)
没有评论:
发表评论